PRINCE2

Controlled projects, from mandate to handover

I use PRINCE2 (Projects in Controlled Environments) to run infrastructure projects where several teams and suppliers must land one change safely, such as a data centre build, a network refresh or a set of site migrations. This page explains the method: its principles, roles, processes and stages, and how tolerances and exceptions keep a project under control. It also shows how I tailor it, and how I find what is wrong when a project drifts.

  • Seven principles
  • Project board
  • Seven processes
  • Stages and gates
  • Tolerances
  • Business case
  • Product based planning
  • Risk and issues
  • Tailoring
A project moving stage by stage, with the board deciding at each gate A project moves along four stages: initiate, design, build and close. The project board sits above them, sends authority down to each gate and receives highlight reports back. Below, teams and suppliers receive work packages from the current stage and send checkpoint reports up. gate gate gate authorise highlights work checkpoints Project boarddecides at each gate Initiateplan it Stage 2design Stage 3build Closehand over Teams and supplierswork packages One stage at a time, a decision at every gate
Live view · one stage at a time, decided at each gate
PRINCE2

A method for projects with clear decisions

PRINCE2 (Projects in Controlled Environments) is a project method now owned by PeopleCert. It sets out who decides what, when they decide it, and what they need in front of them to decide well. This page follows the 7th edition, published in 2023. I use the method on infrastructure projects where several teams and suppliers must land one change safely. Choose an element to see what it holds.

The five integrated elements of PRINCE2 PRINCE2 has five integrated elements. People sit at the centre, linked to the principles, the practices, the processes and tailoring, all inside the project context. Choosing an element lists what it contains: seven principles, the parts of the people element, seven practices with the question each answers, seven processes, and the parts of the project context that tailoring responds to. PROJECT CONTEXT Principlesalways apply Practicesused throughout Peopleat the centre Processesstart to close Tailoringfit the context Seven principles1Ensure continued business justification2Learn from experience3Define roles, responsibilities and relationships4Manage by stages5Manage by exception6Focus on products7Tailor to suit the project People1Leadership and decision making2Culture and ways of working3Communication with stakeholders4Building and running the team5Change in the business that receives it6Relationships with suppliers Seven practices1Business case: why are we doing this?2Organizing: who decides and who does?3Plans: how, how much and when?4Quality: what must it be like?5Risk: what if?6Issues: what is the impact?7Progress: where are we, should we go on? Seven processes1Starting up a project2Directing a project3Initiating a project4Controlling a stage5Managing product delivery6Managing a stage boundary7Closing a project Project context1Size, complexity and risk of the work2Delivery approach: linear, iterative or both3Standalone, or part of a programme4Suppliers and the contracts with them5Rules of the sector, such as financial regulation6How mature the organisation already is

Swipe sideways to see the whole diagram.

The seven principles are what make a project a PRINCE2 project. If one is missing, the method is not being used, however many templates are filled in. They cannot be tailored away.

The 7th edition puts people at the centre: leadership, culture, communication, teams and the change the business has to make to use what the project delivers. A project can follow every process and still fail if nobody leads it or nobody adopts the result.

The seven practices, called themes before the 7th edition, are the aspects of project management that run the whole way through. Each one answers a question the project board keeps asking.

The seven processes say who does what, and when, from the first idea to the last handover. Each process is a set of activities, with clear inputs, outputs and decisions.

Everything else is shaped to the project context. A two month site migration and a three year data centre programme use the same principles, but very different amounts of paperwork, stages and reporting.

Animation

Where it came from

YearWhat happened
1989The CCTA (Central Computer and Telecommunications Agency) adopted PRINCE as the UK government standard for IT projects.
1996PRINCE2 was released as a generic method for any kind of project, not only IT.
2009A major refresh, known as PRINCE2:2009.
2013Ownership moved from the Cabinet Office to AXELOS, a joint venture with Capita.
2017The PRINCE2 2017 update, later renamed the 6th edition, with more on tailoring.
2021PeopleCert bought AXELOS, and with it PRINCE2, ITIL (IT Infrastructure Library) and MSP (Managing Successful Programmes).
2023The 7th edition: themes renamed practices, people added at the centre, and sustainability added as a performance target.

What it is not

  • It is not a technical method. It does not tell me how to design a network or build a data hall. That stays with the specialists, the design authority and the standards they follow.
  • It does not cover programme or portfolio management. MSP and the portfolio guidance sit above it.
  • It does not replace agile delivery. It governs around it, and PRINCE2 Agile, launched in 2015, shows how the two fit together.
  • It is not paperwork for its own sake. Every product should earn its place, and tailoring is a principle, not an option.

The seven practices

PracticeThe question it answersWhat it produces
Business caseWhy are we doing this, and is it still worth it?Business case, benefits management approach
OrganizingWho decides, who does the work, and who checks?Roles, the project management team, communication management approach
PlansHow, how much and when?Project, stage, team and exception plans
QualityWhat must the products be like to be accepted?Product descriptions, quality management approach, quality register
RiskWhat might happen, and what will we do about it?Risk management approach, risk register
IssuesWhat has happened, and what is its impact?Issue management approach, issue register, issue reports
ProgressWhere are we, where are we heading, and should we carry on?Tolerances, highlight, end stage and exception reports

The 7th edition uses the American spelling for the Organizing practice, so I keep its official name. The questions follow the wording used in PRINCE2 training.

Architecture work in the same programmes follows the ADM (Architecture Development Method) of TOGAF (The Open Group Architecture Framework), on my TOGAF page.

Principles

Seven principles that cannot be tailored away

The principles are the part of PRINCE2 that never changes. Processes, documents and meetings can all be scaled up or down, but a project without these seven is not being run with PRINCE2. Here is what each one means to me on infrastructure work.

  1. Ensure continued business justification. There must be a good reason to start, and it must still hold at every stage boundary. If a data centre move no longer pays back because the lease was extended, the board should stop or reshape it, not finish it out of habit.
  2. Learn from experience. I read the lessons from the last refresh before planning the next one, record new lessons as they happen, and pass them on at closure. Most painful surprises on site migrations have happened to someone before.
  3. Define roles, responsibilities and relationships. Everyone knows who decides, who does the work and who checks it, including the suppliers. The 7th edition added relationships, because a board that never talks to the delivery teams decides blind.
  4. Manage by stages. The project is split into management stages, and the board commits to one stage at a time. Long stages hide problems; short stages cost meetings. I set the boundaries where real decisions fall, such as design sign off or the first pilot site.
  5. Manage by exception. Each level gets targets with tolerances and is left to get on with it. Only a forecast breach goes up. This keeps senior people out of the detail without leaving them in the dark.
  6. Focus on products. Plans start from what must be delivered and what good looks like, such as a tested site network or an accepted handover pack, not from a list of activities. Quality criteria are agreed before the work starts.
  7. Tailor to suit the project. The method is shaped to the size, risk and context of the work. A small migration might combine several roles and use one combined report. A regulated bank refresh needs more formal control.

Checking the principles are alive

PrincipleHow I can tell it is workingWarning sign
Business justificationThe business case is updated and reviewed at every stage boundaryThe business case was written once, for funding, and never opened again
Learn from experienceLessons are logged during the work and read at the next start upThe lessons report is written at closure and filed
Roles and relationshipsEach decision has one named owner, and suppliers know their reporting lineDecisions are made in corridors, or by whoever shouts loudest
Manage by stagesThe board authorises one stage at a time against a stage planOne approval at the start, then nothing until go live
Manage by exceptionForecast breaches reach the board early, with optionsOverruns are discovered at the end, or the board reviews every detail weekly
Focus on productsProduct descriptions with quality criteria exist before work packages go outWork is tracked only as tasks and percentages complete
Tailor to suitThe tailoring is written down in the initiation documentation, with reasonsEvery template is filled in, whatever the size of the project
Organisation

Who decides, and who just needs to know

Most projects that drift have a decision problem, not a technical one. PRINCE2 fixes that by naming one owner for each kind of decision and a clear line for reports. Step through the structure to see what flows up and down.

Who decides in a PRINCE2 project, and how information flows Four bands, top to bottom. The business layer sits outside the project. The directing level holds the change authority, the executive, the senior user, the senior supplier and project assurance. The managing level holds the project manager and project support, and the delivering level holds three teams, each run by a team manager. Packets show the mandate and tolerances flowing down, work packages going to teams, checkpoint and highlight reports flowing up, and an exception escalating one level at a time. OUTSIDE THE PROJECT DIRECTING MANAGING DELIVERING Business layercorporate or programme Change authoritydelegated Executivebusiness Senior userusers Senior suppliersuppliers Assuranceindependent project board Project managerday to day Project supportlogs and plans Network teamteam manager Cabling supplierteam manager Server teamteam manager mandate, project tolerances stage plan, tolerances highlight reports exception report beyond project tolerance work packages checkpoint reports checks requests for change Four levels: one decides, one directs, one manages, one delivers The business layer gives the mandate and project tolerances The board authorises one stage at a time, with stage tolerances The project manager hands out work packages with tolerances Team managers report progress in checkpoint reports The project manager reports to the board in highlight reports A forecast breach goes up one level as an exception Assurance checks for the board; change authority decides small changes

Swipe sideways to see the whole diagram.

Step 1
  1. PRINCE2 separates four levels. The business layer sits outside the project and sets its objectives. The project board directs, the project manager manages day to day, and team managers deliver. Each level only needs to know enough to do its own job.

  2. The business layer, which might be corporate leadership, a programme or a customer, writes the mandate that triggers the project. It appoints the executive and sets project tolerances: how far time, cost and the other targets may move before it must be asked.

  3. The project board has three interests. The executive owns the business case and has the final say. The senior user speaks for the people who will use the result, and the senior supplier for those who build it. The board authorises one stage at a time.

  4. The project manager turns the stage plan into work packages for each team, each with its own tolerances. On a site migration that might be the network team, a cabling supplier and the server team, each with a team manager.

  5. Team managers report on a set rhythm in checkpoint reports: what was done, what is next, and any issues or risks. Problems inside a work package's tolerance stay with the team manager.

  6. The project manager sends highlight reports to the board, usually every week or two, with help from project support, which keeps the project log and plans up to date. The board does not need to meet to read them.

  7. When a forecast shows a stage tolerance will be breached, the project manager sends an exception report to the board with options. If the project tolerance would be breached as well, the board must go to the business layer.

  8. Project assurance checks on the board's behalf that the project is being run well. It must be independent of the project manager. The board can delegate decisions on small changes to a change authority, often with a change budget.

Each role on a real project

RoleWho it might be on a data centre moveWhat they decide or do
ExecutiveThe IT director who owns the budgetOwns the business case. Final say on the board.
Senior userHeads of the business teams whose services moveSpecifies needs and acceptance criteria. Accountable for the benefits.
Senior supplierThe infrastructure lead, and the main supplier's delivery directorCommits resources. Accountable for the quality of what is built.
Project assuranceAn architect from the design authority, a finance partner, a service ownerChecks independently for each board member that the project is being run well.
Change authorityA smaller group, such as the project manager and the lead architectDecides on changes within a delegated limit and change budget.
Project managerThe person who runs the move day to dayPlans, delegates work packages, reports and escalates exceptions.
Team managerThe network lead, the cabling supplier's site leadDelivers work packages and reports in checkpoint reports.
Project supportA PMO (project management office) analystKeeps the project log, plans and records. Runs configuration control.

Combining roles

  • One person can hold more than one role, and one role can be shared, except where independence matters.
  • The executive is always one person, so there is one owner of the business case.
  • The executive and project assurance must not also be the project manager, a team manager or project support.
  • The senior user and the senior supplier can each be several people, but a big board decides slowly. I aim for one voice for each interest.

On infrastructure work the senior supplier is often split between an internal lead and a main contractor. I make sure the contract and the board role say the same thing, so the supplier's reporting line is clear from day one.

People

Projects are delivered by people, not documents

The 7th edition made people one of its five elements, alongside the principles, practices, processes and project context. It covers leadership, culture, communication, teams and the change the business must make to use what the project delivers. This is how I apply it.

Leading across teams

Most of my projects mix internal engineers, several suppliers and the client's own staff. Nobody reports to everyone. I lead through clear goals, short feedback loops and credit given in public.

Culture

A team that hides bad news makes management by exception useless. I reward early warnings, so an engineer who says a date will slip is thanked, not blamed.

Communication

The communication management approach sets who hears what, how and how often. On a site migration it covers users, the service desk, suppliers, site managers and the people who sign off outages.

Change for the business

A new network or data centre only pays back if people use it well. I plan the change for the receiving teams, such as training for the service desk and new runbooks for operations, as products in their own right.

Relationships with suppliers

I treat suppliers as part of the team, with team managers who report like everyone else. Their contracts match the work packages, so the commercial and project views agree.

Teams that keep learning

After each wave of a rollout the team reviews what slowed it down, and the next wave changes. Lessons recorded during the work beat lessons remembered at the end.

Who hears what

AudienceWhat they needHow oftenHow
Project boardProgress against tolerances, risks, decisions neededEvery one or two weeks, and at each stage boundaryHighlight report, board meeting at stage end
Users and site staffWhat changes, when, and what they must doBefore each wave, and on the dayNotices, site briefings, a contact for the day
Service desk and operationsWhat is moving, known issues, new runbooksBefore go live and through hypercare, the period of extra support after go liveHandover sessions, knowledge articles
SuppliersWork packages, dates, access, acceptance criteriaWeekly, through their team managersWork package, checkpoint calls
Change advisory boardWhat will change, the risk and the way backFor each change windowChange requests

A typical communication plan for an infrastructure project. Each organisation sets its own rhythm.

Processes

Seven processes, from mandate to closure

The processes describe who does what, from the first idea to the last handover. Most of them are run by the project manager. The project board runs one, Directing a project, all the way through, and the teams run another. Step through a project to see how the work and the decisions flow.

The seven PRINCE2 processes across the life of a project A grid of the seven processes. Columns show pre project, initiation, delivery stages and the final stage. Rows show directing, managing and delivering. Directing a project spans the whole project across the top. Starting up comes before the project, and initiating forms the first stage. Controlling a stage and managing a stage boundary repeat for each delivery stage, with managing product delivery underneath them. Closing a project sits in the final stage. Packets show the mandate, authorisations, work packages and reports moving between them. Pre project Initiation Delivery stages Final stage DIRECTING MANAGING DELIVERING Business layer Directing a projectthe project board, throughout Starting upa project Initiatinga project Controlling a stageevery stage Stage boundaryplan the next Closinga project Managing product deliveryteam managers and suppliers mandate request to initiate authorise initiation request to deliver authorise stage highlights work packages checkpoints, products end stage report closure recommendation Starting up: is the project worth initiating? The board authorises initiation Initiating: plans, controls and the full business case Controlling a stage: work out, reports up Managing product delivery: teams build and check products Stage boundary: report the stage, plan the next one Closing: hand over, evaluate, recommend closure

Swipe sideways to see the whole diagram.

Step 1
  1. Before any real money is spent, the mandate is turned into a project brief and an outline business case, the executive and project manager are appointed, lessons from earlier projects are gathered, and the initiation stage is planned. The question is simple: is this worth initiating?

  2. The project board runs this process from start to finish. It authorises initiation, then the project, then each stage or exception plan, gives direction when asked, and authorises closure. Most of its work is done by reading reports and deciding, not by meeting.

  3. The initiation stage builds the foundations: the management approaches for risk, quality, issues, communication and the rest, the project plan, the detailed business case and the project controls. Together they form the project initiation documentation, the baseline the board approves.

  4. Inside each stage the project manager authorises work packages, reviews progress, handles issues and risks, reports highlights to the board and takes corrective action within tolerance. Anything forecast beyond tolerance is escalated.

  5. Team managers accept a work package, build the products, check them against their quality criteria and hand them back, reporting in checkpoint reports. Suppliers can run their own methods inside this process, including agile ones.

  6. Near the end of every stage except the last, the project manager reports on the stage, updates the project plan and business case, and plans the next stage. The board then decides whether to carry on. An exception plan is produced here too.

  7. In the final stage the products are handed over and accepted, the project is evaluated against its baseline, lessons and follow on actions are recorded, and closure is recommended to the board. The business layer then tracks the benefits that come later.

Each process on an infrastructure project

ProcessWho leads itMain outputsOn a network refresh
Starting up a projectExecutive and project managerProject brief, outline business case, initiation stage planIs the refresh worth scoping? Which sites, which suppliers, which lessons from the last one?
Directing a projectProject boardAuthorisations, direction, closureStage approvals, decisions on scope, budget and supplier changes
Initiating a projectProject managerProject initiation documentation, project plan, detailed business caseSurvey results, design approach, wave plan, test strategy, budget
Controlling a stageProject managerWork packages, highlight reports, issue and risk recordsEach migration wave, with daily progress and issues on the night
Managing product deliveryTeam managersProducts, checkpoint reports, quality recordsConfigured and tested switches, cabling certificates, as built drawings
Managing a stage boundaryProject managerEnd stage report, next stage plan, updated business caseAfter the pilot site: what we learned, and the plan for the next ten sites
Closing a projectProject managerEnd project report, lessons report, follow on actionsHandover to operations, support acceptance, decommissioning list
Stages

Commit one stage at a time, decide at every gate

Manage by stages is the principle I lean on most. It lets a board approve a large investment without signing a blank cheque, because each stage is approved only when the one before it has shown what it set out to show.

Management stages and delivery steps on a network refresh A timeline with four management stages across the top: initiation, stage 2 for design, stage 3 for pilot and build, and stage 4 to migrate and close, separated by gates. Below, six delivery steps run as bars, several of them crossing a gate: surveys, design, procurement, pilot and build, migration waves and handover. One step shows stage 3 split into a pilot stage and a build stage with an extra gate. Management stages: decisions Delivery steps: the work gate gate gate close Initiationplan it Stage 2design Stage 3pilot and build Stage 4migrate, close Stage 3apilot siteStage 3bbuild extra gate Site surveys High and low level design Procure and stage kit Pilot, build and test Migration waves Handover The board commits to one management stage at a time Delivery steps often run across stage boundaries At a gate: end stage report, next stage plan, updated business case Where risk is high, I add a gate after the pilot The final stage includes the work of closing the project

Swipe sideways to see the whole diagram.

Step 1
  1. Management stages are the chunks the board commits to, one at a time. There are at least two: an initiation stage, and one or more stages to deliver. Each ends with a decision about whether to carry on.

  2. The technical work does not stop politely at a stage boundary. Design work can finish early in stage 3, and surveys for later sites can run while the first are designed. PRINCE2 keeps the two views apart: stages are for control, steps are for doing.

  3. At the end of each stage the project manager sends an end stage report, the plan for the next stage and an updated business case and project plan. The board decides to carry on, change course or stop. Stopping early is a valid, and sometimes the best, outcome.

  4. I set stage boundaries where real decisions fall. On a large rollout I put a gate straight after the pilot site, so the board approves the full rollout only once the pilot has proved the design, the runbook and the supplier.

  5. There is no separate closing stage. The last delivery stage also hands over the products, gets them accepted, evaluates the project and recommends closure. Benefits that come later are tracked by the business layer.

How long should a stage be?

QuestionShorter stagesLonger stages
ControlMore decision points, problems surface soonerFewer decisions, the board can lose sight of the work
OverheadMore end stage reports and board timeLess reporting overhead
PlanningEach stage plan can be detailed and reliableDetailed plans go stale before the stage ends
Good fitNew technology, a new supplier, regulated or high risk workRepeat work with a proven design, such as wave 20 of 30
Tolerances

Manage by exception, with numbers agreed in advance

Tolerances are how PRINCE2 keeps senior people out of the detail without leaving them in the dark. Each level is given targets with room to move. Inside that room, problems are dealt with and reported. Outside it, they go up one level, early and with options.

Tolerances and management by exception On the left, a chart of cost to date against weeks, with the planned line inside a tolerance band that widens over time. Actual cost tracks the plan to today. A forecast line then leaves the band, marked as a forecast breach, and a new exception plan band is drawn around it. On the right, four levels are stacked: the business layer, the project board, the project manager and the team manager. Each delegates tolerances to the level below, and exceptions travel up one level at a time. cost to date weeks plan tolerance forecast breach exception plan today project stage work package Business layersets project tolerances Project boardsets stage tolerances Project managersets work package tolerances Team managerworks inside them Each level delegates targets with tolerances to the next Inside the band: the project manager deals with it Forecast beyond stage tolerance: exception report to the board The board approves an exception plan with new tolerances Beyond project tolerance: the board refers it to the business layer

Swipe sideways to see the whole diagram.

Step 1
  1. Every plan has targets, and every target has a tolerance: how far it may move before the level above must be told. The business layer sets project tolerances, the board sets stage tolerances, and the project manager sets tolerances for each work package.

  2. While actuals and the forecast stay inside the band, the project manager deals with problems and reports them in the next highlight report. The board does not need to meet, and nobody is surprised.

  3. The trigger is a forecast, not an actual. As soon as I can see the stage will end outside its tolerance, I send an exception report to the board, with the cause, the options and my recommendation. Waiting until it happens removes the options.

  4. If the board agrees, I produce an exception plan to replace the rest of the stage, with new tolerances. The board can also cut scope, add money or time within the project tolerance, or ask for a premature close.

  5. If the forecast would breach the project tolerance too, the board cannot approve it alone. It refers the exception to the business layer, which decides whether the project still makes sense and on what terms.

Seven performance targets

Performance targetExample tolerance on an infrastructure projectWhere it is set
Time± 2 weeks on a stage, ± 4 weeks on the projectProject plan and stage plans
Cost± 10% of the stage budgetProject plan and stage plans
ScopeMust have sites fixed; could have sites may move to a later phaseProject product description, plans
QualityNo priority 1 defects open at handover; other defects within an agreed numberProject product description, product descriptions
BenefitsYearly savings within 10% of the business case figureBusiness case
RiskNo single risk above an agreed exposure without the board's approvalRisk management approach
SustainabilityAt least 90% of removed equipment reused or recycled, power per rack within the design limitSustainability management approach

Tolerances are examples, labelled indicative. Each board sets its own. Sustainability became the seventh performance target in the 7th edition.

Try it: inside tolerance, or an exception?

Set a stage budget and length, the tolerances the board gave me, and my forecast for the end of the stage. The tool says who decides and what I send. The figures are indicative.

Cost

£600k
± 10%
115%
£150k

Time

12 weeks
± 2 weeks
week 13
4 weeks
Cost
Time
Cost forecast
£690k, £90k over plan, tolerance ± £60k
Time forecast
week 13, 1 week late, tolerance ± 2 weeks
Who decides
The project board
What I send
Exception report, then an exception plan if agreed

Forecast beyond stage tolerance. I send an exception report to the project board now, with options and a recommendation. If the board agrees, I write an exception plan for the rest of the stage.

Business case

Still worth it? Asked at every gate

Continued business justification is the first principle for a reason. A project that made sense in January can stop making sense by June. The business case is a living document that the board checks at every stage boundary, not a funding form.

How the business case evolves, and why benefits come after closure Five business case documents along a timeline: outline at starting up, detailed at initiation, updated at each gate, confirmed at closing, and benefits reviews after closure. At a gate, a red branch shows the project closing early if it is no longer justified. Below, a cumulative net value line dips while the project spends, then rises after closure and crosses zero at payback. payback cumulative net value project costs closure Outlinestarting up Detailedinitiation Updatedeach gate Confirmedclosing Benefitsafter closure Close early Outline business case: is it worth initiating? Detailed business case in the initiation documentation At every gate: still desirable, viable and achievable? At closing: confirm the benefits so far, hand over the rest After closure: benefits reviews until payback and beyond

Swipe sideways to see the whole diagram.

Step 1
  1. In Starting up a project the executive owns an outline business case: the reasons, the options considered, the expected benefits and costs, the timescale and the main risks. It only needs to be good enough to decide whether initiation is worth paying for.

  2. In initiation the case is refined with real costs from the project plan and the risks from the risk register. The benefits management approach says how, when and by whom each benefit will be measured, often long after the project has closed.

  3. At each stage boundary the business case is updated with actual costs and new forecasts, and the board asks whether the project is still desirable, viable and achievable. If it is not, the right answer is to close early, and that is a success for the method.

  4. At closing the project confirms the benefits already achieved, and the benefits management approach passes to the business layer. The project manager is not left holding promises the project cannot keep.

  5. Most infrastructure benefits come later: lower support costs, fewer outages, a data centre lease ended. Benefits reviews track them against the business case until payback and beyond. The senior user is accountable for them.

What goes in a business case

PartWhat I put in it on an infrastructure project
ReasonsWhy now: end of life equipment, a lease ending, a merger, a regulatory finding, or an outage that must not happen again
Business optionsDo nothing, do the minimum and do something, each costed honestly. Do nothing is often more expensive than it looks.
Expected benefitsMeasurable and owned: lower support and power costs, fewer priority 1 incidents, faster site moves
Expected disbenefitsWhat gets worse: training time, a period of dual running, a temporary loss of a feature
TimescaleThe project period, and when each benefit is expected to arrive
CostsCapital and operating costs, including support, licences, power and decommissioning
Investment appraisalPayback period and net present value over the life of the assets
Major risksThe few risks that could change the decision, taken from the risk register
Products

Plan the products first, then the work

Focus on products is the principle that changes plans the most. Before anyone lists tasks, I agree what will be delivered and what good looks like. On a network refresh that means the HLD (high level design), the LLD (low level design), the tested network and the handover pack, each with its own description.

Product based planning for a network refresh At the top, a product breakdown structure for a refreshed site network, split into design, equipment, installed network and handover, each with three products. Below, a product flow diagram puts the products in order in two rows. The first runs from the survey through high level design, low level design, bill of materials, delivered kit and staged kit. The second runs from racked and cabled through configured, tested and the as built pack to accepted. A packet follows the flow from start to finish. Product breakdown structure Site surveyHigh level designLow level designDesignBill of materialsDelivered kitStaged kitEquipmentRacked and cabledConfigured switchesTested networkInstalled networkAs built packSupport acceptanceDecommission listHandover Refreshed site network Project product description: quality expectations and acceptance criteria Product flow diagramSite surveyHLDLLDBill of materialsDelivered kitStaged kitRacked, cabledConfiguredTestedAs built packAccepted Start from the end product and what the customer will accept Break it down into the products that make it up Describe each product, with quality criteria and an approver Put the products in the order they must be made Only then add activities, people and dates

Swipe sideways to see the whole diagram.

Step 1
  1. Planning starts with the project product description: what the project will hand over, and the customer's quality expectations and acceptance criteria. Here the product is a refreshed site network, accepted when it passes the agreed tests and support has signed it off.

  2. The product breakdown structure splits the end product into the products that make it up, grouped for clarity. It includes the dull products that projects forget, such as the as built pack, support acceptance and the list of kit to decommission.

  3. Each important product gets a product description: its purpose, what it is made of, where it comes from, its quality criteria, how it will be checked and who approves it. Writing these first is how focus on products becomes real.

  4. The product flow diagram shows the order in which products must be made, and which depend on which. The low level design needs the survey, the staged kit needs the design and the delivered kit, and so on.

  5. Only now are activities, people, durations and dates added, and the critical path appears from the flow. Plans built this way are harder to fool: a task can be 90% done for weeks, but a product is either approved or it is not.

A product description I would write

Title
Low level design for one site
Purpose
Gives engineers everything needed to build and test the site without guessing
Composition
Device list and roles, port maps, addressing, VLANs, routing, security policy, configuration templates, test plan
Derivation
High level design, site survey, design standards, vendor guidance
Quality criteria
Traces to the high level design; every port and address allocated; tests have pass marks; no open design decisions
Quality method
Peer review by a second engineer, then a design authority review
Approver
Lead architect, with operations signing that it can be supported

Why I plan this way

  • Scope arguments become concrete. If a product is not in the breakdown, it is not in the project.
  • Suppliers know what done means before they start, because the quality criteria are in the work package.
  • Progress is measured in approved products, which cannot be 90% finished.
  • The handover products are planned from day one, so operations are not handed a surprise at the end.

This is the same habit as my test packs with pass marks: agree what good looks like before the work starts.

Quality

Agree what good looks like before anyone builds

The quality practice separates quality planning, which happens before the work, from quality control, which checks the products as they are made. Acceptance is the end of the chain: the people who will use and support the result say it is fit for purpose.

Quality planningWhat it holdsExample
Customer's quality expectationsWhat the customer expects of the end product, in their own words, then made measurableCalls and trading screens unaffected during the move; no loss of resilience
Acceptance criteriaThe measurable list the end product must meet to be acceptedAll tests passed, monitoring in place, support signed off, as built pack complete
Product descriptionsQuality criteria and the quality method for each productLow level design reviewed by a peer and the design authority
Quality management approachStandards, methods, records and responsibilities for quality on this projectWhich tests, which reviewers, which tools, where results are kept
Quality registerA record of every planned and completed quality activityEach review and test, with its date, result and sign off

The quality review technique

Chair

Runs the review and makes sure it reaches a decision: approved, approved with changes, or not approved.

Presenter

Introduces the product and answers questions. Usually its author or the team that made it.

Reviewer

Checks the product against its quality criteria before the meeting, and brings questions, not opinions.

Administrator

Records the actions and the result, and updates the quality register.

How the practice maps onto infrastructure testing

Test on my projectsWhat it provesWho accepts it
Design reviewThe design meets the requirements and the standardsLead architect and design authority
FAT (factory acceptance test)Kit is built and configured correctly before it leaves the bench or the factoryTeam manager, with the supplier
SAT (site acceptance test)The installed network works on site, against the test packProject manager, with site and service owners
Operational acceptanceOperations can monitor, support and recover it: runbooks, alerts, spares and accessThe service owner and support teams
User acceptanceUsers can work as before, or betterThe senior user

The test pack and its pass marks are written with the design, as on my design authority page. PRINCE2 adds the record: every check is planned in the quality register and signed off by a named person.

Risk and issues

Risks are what might happen, issues are what has

The Risk practice deals with uncertain events that would affect the objectives. The Issues practice, which replaced the Change theme in the 7th edition, deals with things that have already happened, including requests for change. Step through how an issue is handled, and who may decide it.

An issue, from capture to decision Three issue types on the left, a request for change, an off specification and a problem or concern, flow into capture, then assess, then recommend. From recommend, the decision goes to one of four levels on the right: the project manager within tolerance, the change authority within the change budget, the project board beyond tolerance, or the business layer beyond the project. The decision then flows to implement, where plans and records are updated. Request for change Off specification Problem or concern Issue types Captureproject log Assessthe impact Recommendwith options Project managerwithin tolerance Change authoritysmall changes Project boardbeyond tolerance Business layerbeyond the project Implementupdate and tell daily log if informal issue register if formal time, cost, scope, quality, benefits, risk cost of each option plans, registers, baselines updated Capture: log it and decide whether it is formal Assess: what does it do to the targets and the business case? Recommend: options, each with its cost and effect Decide inside tolerance: project manager or change authority Decide beyond tolerance: the board, or the business layer Implement: update plans and records, and tell whoever raised it

Swipe sideways to see the whole diagram.

Step 1
  1. An issue is anything that has happened and needs attention. PRINCE2 names three kinds: a request for change, an off specification where a product does not or will not meet its specification, and a problem or concern. Small ones go in the daily log; formal ones go in the issue register with an issue report.

  2. I assess the impact on every performance target and on the business case, and check whether it creates or changes any risks. A small change to a cabling route can still move a migration date.

  3. I set out the options, each with its cost, its effect on the plan and its risks, and recommend one. Doing nothing is often an option worth costing.

  4. If the fix fits inside tolerance, I decide as project manager. The board can also delegate decisions on requests for change to a change authority with a change budget, which stops small changes queuing for a board meeting.

  5. If it would breach stage tolerance, it goes to the board as an exception. If it would breach project tolerance, the board refers it to the business layer. Each level decides only what it has the authority to decide.

  6. The decision is carried out, plans and baselines are updated under configuration control, the registers record the outcome, and the person who raised the issue hears what happened to it.

The risk procedure

  1. Identify. Find threats and opportunities, and describe each with a cause, an event and an effect, so it can be managed.
  2. Assess. Estimate likelihood, impact and proximity, then look at the overall exposure against the risk tolerance.
  3. Plan. Choose a response, and name a risk owner and an actionee for it.
  4. Implement. Carry out the response, check it works and keep the risk register current.
  5. Communicate. Report risks in highlight and end stage reports throughout, not only at the end.

A few lines from a risk register

RiskOwnerResponse
Network kit arrives late because of lead timesSenior supplierOrder long lead items in the design stage; agree substitute models
Legacy applications fail after the move because of hard coded addressesSenior userDiscovery of dependencies; test moves in a pilot; address translation as a fallback
Key engineer unavailable on the cutover weekendProject managerTwo trained engineers per role; runbooks anyone can follow
Power or cooling in the new hall below design limit at full loadSenior supplierLoad test before migration; stage the moves by power draw

Indicative risks from infrastructure moves, with owners and responses.

Responses to threats and opportunities

ResponseForExample on a data centre move
AvoidThreatMove the change window away from the quarter end, so a failure cannot hit trading
ReduceThreatStage and test all kit on the bench first, so fewer faults reach site
FallbackThreatA tested rollback plan if the cutover fails, with a go or no go point
TransferThreatFixed price installation, so a supplier carries the cost of its own rework
ShareBothA gain share deal with a supplier for finishing early
AcceptThreatA small risk with a cheap fix if it happens, recorded and watched
Exploit or enhanceOpportunityBring a lease end forward once the new hall is proven early

The response names follow PRINCE2 training material, and vary a little between editions. A risk budget, held by the executive, pays for planned responses and is not a reserve for overruns.

Progress

Reports on a rhythm, escalations when they matter

The progress practice answers three questions: where are we, where are we heading, and should we carry on? It uses tolerances, a steady rhythm of reports and records, and event driven reports for anything that cannot wait.

The reporting rhythm in a stage On the left, team managers, the project manager and the project board are stacked from bottom to top. Checkpoint reports rise often from the teams to the project manager, and highlight reports rise less often to the board. On the right, an eight week calendar shows checkpoint reports every week and highlight reports every two weeks. An issue report and an exception report are raised when events happen, and an end stage report closes the stage. A marker moves along the weeks. Project boardreads, decides Project managerproject log Team managerswork packages checkpoints highlights Highlight reports to the board Event driven reports Checkpoint reports from teams 1 2 3 4 5 6 7 8 week exception report end stage issue report

Swipe sideways to see the whole diagram.

Animation
  • Checkpoint: team manager to project manager
  • Highlight: project manager to board
  • Exception: when a forecast breaches tolerance
  • End stage: at the gate

Time driven and event driven controls

ControlTime driven or event drivenExample
Highlight reportTime drivenEvery week or two during a stage
Checkpoint reportTime drivenWeekly, or daily during a migration weekend
Authorisation of a stageEvent drivenAt each stage boundary
Exception reportEvent drivenAs soon as a forecast breach is clear
Issue reportEvent drivenWhen a formal issue needs a decision
End stage and end project reportsEvent drivenAt each gate, and at closure

Forecasts, not just actuals

  • Every highlight report forecasts the end of the stage against its tolerances, not only what was spent.
  • I show progress as products approved against plan, which is harder to round up than tasks.
  • A good report fits on one page and ends with the decision the board is being asked for, if there is one.
  • Most of this now lives in a tool, such as a project system or ServiceNow, with the board reading a dashboard. The rhythm matters more than the format.

Management products

KindManagement productWhat it is for
BaselineBusiness case, project brief, project product descriptionWhy, what and for whom. Approved and then changed only under control.
BaselineProject initiation documentation, plans (project, stage, team, exception)How the project will be run and delivered
BaselineManagement approaches: benefits, change, commercial, communication, digital and data, issue, quality, risk, sustainabilityThe rules for each practice on this project
BaselineProduct descriptions and work package descriptionsWhat each product must be, and the work handed to each team
ReportCheckpoint, highlight, end stage, end project, exception, issue and lessons reportsA snapshot at a point in time, for a decision or a record
RecordProject log: daily log, issue register, lessons log, product register, quality register, risk registerLiving records, kept up to date by the project manager and project support

Grouped as in PRINCE2 training material for the 7th edition. Tailoring decides which are separate documents, which are combined and which are a line in a tool.

Tailoring

Tailored to the project, never to the point of losing control

Tailoring is a principle, not an option. The 7th edition shapes everything to the project context: its size, its delivery approach, whether it is part of a programme, its suppliers and its risk. Delivery can be linear sequential, iterative incremental or a hybrid of the two.

Linear sequential

Requirements are fixed early and the work moves through design, build, test and deploy in order. It suits a data centre build or a cabling project, where rework is expensive.

Iterative incremental

Requirements evolve and products are delivered in small increments. It suits automation, portals and tooling, where users learn what they want by using it.

Hybrid

Most of my infrastructure projects are hybrid: the hardware follows a plan, while automation and the operational tooling around it are built iteratively.

Try it: tailor PRINCE2 to a project

Answer five questions about a project. The suggestions are how I would usually start, before talking to the board. The example shown is a medium sized refresh with several suppliers.

How big is it?

Delivery approach

Context

Suppliers

Risk

Project board
An executive, a senior user and a senior supplier, meeting at each gate and deciding by exception in between.
Stages
Initiation, then two or three delivery stages, each ending at a real decision.
Reporting
A weekly or fortnightly highlight report, with checkpoint calls each week.
Documents
Initiation documentation with short approaches for risk, quality, issues and communication.
Delivery approach
Design and build follow a plan, while automation and tooling are built in iterations. Each part gets the tolerance that suits it.
Business layer
Senior leadership sets the project tolerances and receives the benefits.
Suppliers
A commercial management approach, a team manager for each supplier, and one voice for the senior supplier role.
Control
Normal tolerances and a change authority with a small change budget.
Always
The seven principles apply in full, whatever the size.

How PRINCE2 sits beside other methods

PRINCE2Body of knowledgeScrumMSP
What it isA method for running a projectThe PMBOK (Project Management Body of Knowledge) Guide, from PMI (Project Management Institute)A framework for a team delivering in short sprintsA method for a programme of related projects
Main focusGovernance, roles, stages and productsPrinciples and practices for project performanceDelivering working increments, with fast feedbackOutcomes and benefits across several projects
Who decidesProject board, by exceptionDepends on the organisationProduct owner for prioritiesSponsoring group and senior responsible owner
How I combine themThe control frame around the projectA reference for techniques, such as estimatingInside Managing product delivery, for software and automationAbove PRINCE2, as the business layer

Once a project hands over, the service is run with ITIL practices, and the design rules stay with the design authority.

When it goes wrong

Finding what is wrong with a project

Projects fail in a few familiar ways, and the cause is rarely where the symptom appears. A late stage is often a reporting problem, and a failed handover is often a requirements problem. Choose a symptom to see where I look and what I change.

A project health fault finder Five places a project problem can sit, from left to right: the business layer, the project board, the project manager, the team managers and the suppliers. For each symptom, a marker travels to the level where the cause usually lies, and a panel shows what I see and which record I check. Business layermandate, benefits Project boarddirection Project managercontrol Team managersdelivery Supplierscontracts What I see What I check Symptom: Scope keeps growing Work added after calls with users, with no issue raisedIssue register, change budget, product breakdown Symptom: Overrun found at the end of a stage Highlight reports show money spent, not a forecastStage plan, forecast to completion, stage tolerances Symptom: Decisions take weeks Board meetings cancelled, deputies sent without authorityBoard membership, minutes, delegated limits Symptom: Nobody can say if it paid off No benefit owner, and no measurement taken before the projectBusiness case, benefits management approach Symptom: A supplier keeps missing dates Checkpoints say on track until the week it slipsWork package, its tolerances, the contract Symptom: Defects found at handover Products marked complete with no review or test recordQuality register, product descriptions Symptom: The same risks every week Risk register with no owners, no actions and no datesRisk register, risk management approach, risk budget Symptom: Operations refuse the handover No runbooks, monitoring or spares in place at go liveProject product description, acceptance criteria

Swipe sideways to see the whole diagram.

Scope keeps growing. Requests for change are being accepted in conversation, so the plan and the business case no longer match the work. I route every change through the issue procedure, set up a change authority with a small change budget for minor ones, and treat the product breakdown structure as the scope.

An overrun is found at the end of a stage. Reports showed actuals but no forecast, so the breach was visible only once it had happened. Every highlight report I write forecasts the end of the stage against its tolerances, and I raise an exception as soon as the forecast leaves the band.

Decisions take weeks. The board is too big, or its members cannot commit their side. I aim for one voice for each of the three interests, written delegated limits, decisions by exception between meetings with a deadline, and a change authority for small changes.

Nobody can say if it paid off. Benefits were promised but never owned or measured. The senior user is accountable for them, baselines are measured during initiation, and the business layer runs benefits reviews after closure. If a benefit cannot be measured, I say so in the business case.

A supplier keeps missing dates. The work package was vague, or it did not match the contract. I write work packages with products, quality criteria, tolerances and a reporting rhythm, align them with the contract, and hold the senior supplier to account for the supplier's resources.

Defects are found at handover. Products were accepted without being checked against quality criteria, often because there were none. I write product descriptions with quality criteria first, plan every review and test in the quality register, and accept nothing without a record.

The same risks every week. The register has become a list of worries. Each risk needs an owner, a response and an actionee with a date, and the expensive responses need a risk budget the executive has agreed.

Operations refuse the handover. Operational acceptance was never part of the acceptance criteria, so support teams were not involved. I put runbooks, monitoring, spares and training into the project product description from the start, and plan a hypercare period before closure.

Animation

The records I read first

QuestionWhere I lookWhat it tells me
Is the business case still true?Business case, last end stage reportWhether the reasons, costs and benefits still hold
Are we inside tolerance?Latest highlight report, stage planThe forecast against each target, not just the spend
Who has decided what?Board minutes and the daily logWhether decisions are being made, and by the right level
What has changed?Issue register, product registerChanges accepted, and whether baselines were updated
What could hurt us next?Risk registerOwners, responses and dates for the top risks
Is it good enough?Quality registerReviews and tests planned against those done and passed
Have we learned?Lessons logWhether lessons are being acted on during the project, not just recorded

When I join a project that is in trouble, I read these seven records before I talk to anyone. The gaps between them usually show where the problem is. My general fault finding method is on the troubleshooting page.

Engagement

How I run a project, from mandate to benefits

Most of my projects are infrastructure changes with several suppliers: a refresh, a migration or a build. These stages are how I take one from the first conversation to the benefits, and each maps onto a PRINCE2 process.

How I run a PRINCE2 project, from mandate to benefits Seven stages from left to right: engage (mandate), requirements (brief), discovery (survey), design (initiation), build and test (stages), support (handover), lifecycle (benefits). For each stage the panel shows who I work with and what comes out of it. After the lifecycle stage the loop returns to the start. Engagemandate Requirementsbrief Discoverysurvey Designinitiation Buildstages Supporthandover Lifecyclebenefits Step 1 · EngageWho wants it, why now, and who decidesWho I work withWhat comes outExecutive and sponsorBusiness layerService ownersMandate and reasonsExecutive and project managerBoard roles proposedLessons from past projects Step 2 · RequirementsWhat must be delivered, and how wellWho I work withWhat comes outSenior userOperations and supportSecurity and riskProject product descriptionAcceptance criteria with numbersPerformance targetsConstraints and dependencies Step 3 · DiscoveryThe estate, the risks and the suppliersWho I work withWhat comes outSite and estate teamsSuppliersFinance and procurementSurvey and dependency mapOutline business caseFirst risk registerSupplier and contract view Step 4 · DesignPlans, approaches and the full business caseWho I work withWhat comes outProject boardDesign authorityTeam managersProject initiation documentationProduct breakdown and flowStage plan and tolerancesDetailed business case Step 5 · Build and testWork packages out, reports and products backWho I work withWhat comes outTeam managersSuppliersChange advisory boardWork packages with tolerancesHighlight and checkpoint reportsApproved productsEnd stage report at each gate Step 6 · SupportAccepted, supported and closed properlyWho I work withWhat comes outOperations and service deskSenior userSuppliersOperational acceptanceHypercare and exit criteriaEnd project reportLessons report and actions Step 7 · LifecycleBenefits measured long after closureWho I work withWhat comes outBusiness layerSenior userFinanceBenefits reviewsOwners for follow on actionsLessons fed to the next projectAsset and contract records

Swipe sideways to see the whole diagram.

Step 1
  1. I start by finding the person who owns the money and the reason, and making them the executive. Together we turn the mandate into a short brief, propose the board and read the lessons from the last similar project. This is Starting up a project, and it should take days, not months.

  2. I write the project product description with the senior user: what will be handed over, and the measurable acceptance criteria, including what operations need to support it. Targets and tolerances for time, cost, scope, quality, benefits, risk and sustainability are agreed here, so later exceptions are judged against numbers.

  3. Before the plan I find out what is really there: sites, equipment, dependencies, contracts, change freezes and who can work when. The findings feed the outline business case and the first risk register. On migrations, application dependencies are usually the biggest unknown, so I start on them early.

  4. Initiation turns the brief into the project initiation documentation: the management approaches, a project plan built from products, the detailed business case and the tailoring. The technical design runs alongside under the design authority. The board approves the whole package before the first delivery stage starts.

  5. Each delivery stage runs through Controlling a stage and Managing product delivery. Work packages go out with tolerances, checkpoint and highlight reports come back, and issues and risks are handled at the right level. Every change to live services still goes through change control, and each stage ends at a gate.

  6. In the final stage the products are handed over and accepted, including operational acceptance by the teams who will support them. Hypercare covers the first weeks. I write the end project report against the original baseline, record lessons and follow on actions, and recommend closure to the board.

  7. Most benefits arrive after the project closes, so the benefits management approach passes to the business layer, with named owners and dates for each review. Lessons go into the next start up, follow on actions get owners, and the asset and contract records are left accurate for the next refresh.

Functional requirements

What the project must deliver and control.

  • Deliver every product in the project product description, accepted against measurable criteria.
  • Give the board a decision point at the end of every stage, with an updated business case.
  • Escalate any forecast breach of tolerance to the right level quickly, with options.
  • Handle every request for change through one issue procedure, with clear limits of authority.
  • Hand over to operations with runbooks, monitoring, spares and trained support teams.
  • Record lessons during the project and pass them on to the next one.

Non functional requirements

How well the project must be run, with a number wherever one can be agreed.

Reporting
A highlight report every one or two weeks, with a forecast against each tolerance (typical).
Escalation
An exception report within five working days of a forecast breach becoming clear (typical).
Decisions
Board decisions on an exception within ten working days (typical).
Tolerances
Stage cost tolerance of about ± 10% and time tolerance of about ± 2 weeks, set by the board (typical).
Quality
No priority 1 defects open at handover, and a quality record for every product.
Changes
Every change to live services approved through change control, with a tested rollback.
Benefits
Each benefit with an owner, a baseline measure and a review date.
Sustainability
A target for reuse or recycling of removed equipment, agreed with the board (typical).

Numbers are typical starting points. Each board agrees its own.

Projects

Where I have used it

PRINCE2 delivery is part of my governance work. As technical design authority and lead architect I have planned phased rollouts, led blended teams of engineers and vendors, delivered a data centre build from an empty shell, and worked under formal change governance in banking.

AVEVA · 2020 to 2021

A phased rollout to every site worldwide

Planned the network and security transformation as a phased, site by site roadmap, and upgraded every global site remotely during the COVID lockdowns through local enablement, with no delay. Led 7 engineers and architects, coordinated 5 vendors, and safeguarded over £200M of transactional services at 99.99% uptime.

2e2 · 2011 to 2013

The £25M Network Rail data centre build

Delivered the Network Rail data centre build from an empty shell, covering structured cabling, building management systems and mechanical and electrical integration, while leading 3 engineers on finance, transport and government projects.

BNY Mellon · 2018 to 2019

A refresh under strict change governance

Delivered the EMEA (Europe, the Middle East and Africa) network refresh: audit, design and implementation of LAN (local area network), WAN (wide area network), SD-WAN (software defined WAN) and data centre infrastructure. It replaced end of life equipment with minimal impact on global operations. Worked with a blended team of 5 engineers and 4 vendors, and advised on change governance.

Penguin Random House · 2013 to 2015

Benefits that were measured

Post merger infrastructure integration across a multi site estate, including distribution centres. Rationalising infrastructure, support and technology overheads delivered £700k a month in operational savings.

XIDA · 2021 to 2024

Remote site migrations, no critical incidents

Planned and ran remote site migrations across regulated environments with no critical incidents, as lead architect on modernisation programmes from discovery to operational handover.

XIDA · 2025 to now

A phased roadmap for Dyson